Question: Consider the following project network Task Predecessor Time(weeks) M 5 N 3 M 7 D M 6 E N 7 F DE 3 G DE

Consider the following project network Task

Consider the following project network Task Predecessor Time(weeks) M 5 N 3 M 7 D M 6 E N 7 F DE 3 G DE 10 H C,F 8 1- Draw AOA network. 2 marks 2- When will the project finish? 1 mark 3- Identify the critical path? 1 mark 4- What is the total float of activity C? 2 marks 5- What is the schedule of activity E? 2 marks 6- Can activity D be delayed without delaying the entire project? If so, how many weeks? 2 marks