Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 4 B 3 A 5 D B 6 E C D 7 F

Schedule the following activities using CPM:
Schedule the following activities using CPM:
Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 4 B 3 A 5 D B 6 E C D 7 F D 2 G F 3 H E, G 4 UOLLOI COO AWN b. What is the critical path? O A-B-D-E-H O A-C-D-F-G-H O A-B-D-F-G-H O A-B-D-G-H 15 c. How many weeks will it take to complete the project? Number of weeks 24 ints 2 00:38:18 eBook d. Which activities have slack, and how much? O 0.4 weeks ? F. 2 weeks ? G. 2 weeks. OB. 3 weeks H. 2 weeks ? F. 1 week. O B. 1 week ? C. 3 weeks ? F. 2 weeks