Question: Consider the following project schedule; here a, m, b respectively refer to optimistic, most likely and pessimistic completion times of each activity. All times are

Consider the following project schedule; here a,

Consider the following project schedule; here a, m, b respectively refer to optimistic, most likely and pessimistic completion times of each activity. All times are in days. Your are NOT required to draw the project network of do the CPM. Assume that CPM has been performed and it has been determined that BD is the critical path. Answer the following: (1) The expected completion time of activity F= days (5pts) (2) Deetermine, P(T