Question: Consider the following work breakdown structure: 1 Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A, B, C A D 38 50 62


Consider the following work breakdown structure: 1 Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A, B, C A D 38 50 62 BCDEF B E 90 99 108 C End 85 100 115 D F 19 25 31 E End 91 100 115 F End 62 65 68 What is the probability that this project will be completed within 205 days? Consider the following work breakdown structure: Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A, B, C A D 38 50 62 B E 90 99 108 C End 85 100 115 D F 19 25 31 E End 91 100 115 F End 62 65 68 What is the estimated slack time for activity A