Question: Consider the following project: Task ID Duration (Days) Predecessors 2 70 - 3 30 2 4 120 3 5 120 2 6 120 5 7
Consider the following project:
| Task ID | Duration (Days) | Predecessors |
| 2 | 70 | - |
| 3 | 30 | 2 |
| 4 | 120 | 3 |
| 5 | 120 | 2 |
| 6 | 120 | 5 |
| 7 | 120 | 3,6 |
| 8 | 150 | 3,6 |
| 9 | 115 | 3,6 |
| 10 | 130 | 7,9 |
| 11 | 90 | 7,9 |
| 12 | 30 | 7,9 |
| 13 | 120 | 7,9 |
| 14 | 75 | 10 |
| 15 | 30 | 14 |
| 16 | 85 | 6 |
| 17 | 165 | 16 |
| 18 | 90 | 16 |
| 19 | 90 | 17,18 |
| 20 | 20 | 8,11,13,15,19 |
What is the slack for task 8?