Question: Note : Need answer asap Consider the following project. Task Immediate Optimistic Most Pessimistic Crash Normal Crash Predecessors probable Time Cost (100) Cost (100) A

Note : Need answer asap

Note : Need answer asap Consider the following project. Task Immediate Optimistic

Consider the following project. Task Immediate Optimistic Most Pessimistic Crash Normal Crash Predecessors probable Time Cost (100) Cost (100) A 5 6 7 4 10 19 B 7 8 15 7 10 18 C A, B 4 5 2 15 27 D C 9 10 23 8 20 32 E C 8 10 12 7 50 80 F E 5 6 7 4 30 41 G C 5 6 19 5 80 102.5 H D, F, G 6 7 4 50 54 D, F 3 6 15 4 100 124 J H 2 6 3 40 44 K I, J 4 5 3 50 55 SN a. Draw a project network b. Find the critical path and expected project completion time. c. Assuming that management desire a 21 weeks project completion time. What activity should be crashed? d. Activity schedule table after crashing

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!