Question: Consider the following project. Task Pred Time (Weeks) A - 16 B A 6 C B 1 D B 10 E C,D 16 F C,D
Consider the following project.
| Task | Pred | Time (Weeks) |
| A | - | 16 |
| B | A | 6 |
| C | B | 1 |
| D | B | 10 |
| E | C,D | 16 |
| F | C,D | 19 |
| G | E | 8 |
| H | F,G | 13 |
| I | F,G | 6 |
| J | F,G | 9 |
| K | F,G | 16 |
| L | H,I,K | 7 |
| M | J,L | 2 |
If the latest finish requirement is less than the earliest finish time by 2 weeks, what is the slack for task F?