Question: Consider the following project. Task Pred Time (Weeks) A - 16 B A 6 C B 1 D B 10 E C,D 16 F C,D

Consider the following project.

Task Pred Time (Weeks)
A - 16
B A 6
C B 1
D B 10
E C,D 16
F C,D 19
G E 8
H F,G 13
I F,G 6
J F,G 9
K F,G 16
L H,I,K 7
M J,L 2

If the latest finish requirement is less than the earliest finish time by 2 weeks, what is the slack for task F?