Question: Consider the following project. Task Pred Time ( Weeks ) A - 1 6 B A 6 C B 1 D B 1 0 E

Consider the following project.
Task Pred Time (Weeks)
A -16
B A 6
C B 1
D B 10
E C,D 16
F C,D 19
G E 15
H F,G 13
I F,G 6
J F,G 9
K F,G 16
L H,I,K 7
M J,L 2
What is a critical path?
Group of answer choices
A-B-D-E-G-K-L-M
A-B-D-E-G-H-L-M
A-B-D-E-G-J-L-M
A-B-D-F-G-K-L-M

Step by Step Solution