Question: Consider the following project with variable completion times Completion Time (weeks) Activity Predecessor(s) a m b Variance A None 2 5 8 1 B None

Consider the following project with variable

Consider the following project with variable completion times Completion Time (weeks) Activity Predecessor(s) a m b Variance A None 2 5 8 1 B None 1 3 11 2.77 A 3 6 9 1 D B, C 4 5 On 6 0.11 E C, D 1 4. 7 1 If you know the one and only critical path of this project is A-C-E, what are the mean and standard deviation of the project completion time? Select one: a. Mean = 15, SD = 3 b. Mean 15, SD = 1.732 c. Mean = 23, SD = 1.732 d. Mean = 23, SD = 3