Question: Consider the following sequential production process with four machines A, B, C, and D (4 workers operate these machines respectively, one worker per machine). Machine
Consider the following sequential production process with four machines A, B, C, and D (4 workers operate these machines respectively, one worker per machine).
Machine A Machine B Machine C Machine D Framer Handler Stringer Finisher 5 minutes 3 minutes 10 minutes 2 minutes
All flow units need to move through all the above stages sequentially, with the designated task time indicated above. What is the process capacity?
Group of answer choices
6 units per hour
4 units per hour
8 units per hour
3 units per hour
Step by Step Solution
There are 3 Steps involved in it