Question: Consider the following Table and available paths. The overhead (indirect) cost is assumed to be $100 per day. Draw the network, including all steps and

Consider the following Table and available paths. The overhead (indirect) cost is assumed to be $100 per day. Draw the network, including all steps and critical paths. Create a table with detail for cycles; and crash the project for 6 days, i.e., total duration of project 24 days. Highlight the column with minimum total cost. Please explain how all conclusions were obtained.

Consider the following Table and available paths.

Consider the following Table and available paths.

Duration (days) Cost ($) Activity IPA Normal Crash Normal Crash 7 LO LOLO A B C D E F G H . B B, C D, F. E, F G, H 6 8 10 6 4 4 7 2 5 7 4 3 500 550 800 1,200 600 500 700 650 300 640 630 935 1,440 700 590 1,000 950 300 2 4 2 Paths are: 29 ABDGI ABEHI ACEHI ACFGI ACFHI 28 30 25 28

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!