Question: Consider the following table. Predecessor Crash Time Normal Cost in (days) S Crash Cost in s Normal Time (days) 9 5 11 14 Activit y

Consider the following table. Predecessor Crash

Consider the following table. Predecessor Crash Time Normal Cost in (days) S Crash Cost in s Normal Time (days) 9 5 11 14 Activit y A D 400 A A B, C 8 1 5 11 300 600 300 500 500 1000 500 a/ How much is added to the project cost with two days crashed? (5 pts) b/What is the maximum time that can be crashed? How much additional cost is needed? (10 pts)