Consider the following task set, where the last column in the table gives the maximum blocking time to each task. The task deadlines are equal to the task periods. CT B Task T1 3 T2 4 15 T3 6 20 0 332 10 3 Are the tasks schedulable using RM policy for priority assignment, and PIP protocol for protecting shared resource? a) (10 points) Address the question using the utilization based criterion. Note you need to give the schedulability for each task. b) (15 points) Address the question using the response time analysis. Note you need to give the schedulability for each task.
Step by Step Solution
There are 3 Steps involved in it
a Utilizationbased criterion for RM policy To determine the schedulability of tasks using the RateMo... View full answer