Question: Consider the following three projects. Period Project A Project B Project C T=0 ($5,000) ($9,000) ($4,000) T=1 $2,000 $1,500 $900 T=2 $1,200 $2,500 $900 T=3

  1. Consider the following three projects.

Period Project A Project B Project C

T=0 ($5,000) ($9,000) ($4,000)

T=1 $2,000 $1,500 $900

T=2 $1,200 $2,500 $900

T=3 $1,800 $2,500 $200

T=4 $1,800 $2,500 $1,500

T=5 $1,800 $2,500 $1,500

When you have only $9,000 to support the above projects, which project (or projects) should be chosen under NPV method and explain WHY? Use 10 percent discount rate. (6 points)