Question: Consider the following time series data, Month 1 2 3 4 5 6 17 Value 24 113 20 12 119 23 15 Using 4-Period Moving

Consider the following time series data, Month 1
Consider the following time series data, Month 1 2 3 4 5 6 17 Value 24 113 20 12 119 23 15 Using 4-Period Moving Average (4MA) method to forecast the next period, compute the MSE (Mean square Error). Which of the following options is the MSE? Select one: O a. 20.5 O b. 21.4 O c. 20,3 O d. 21.1 O e. 21.0 O 1.20.9 O g. 22.5 O h. 217