Question: Consider the following two mutually exclusive projects, X and Y, and their cash flows information, assuming that the discount rate is 12%: Project Year 0

Consider the following two mutually exclusive projects, X and Y, and their cash flows information, assuming that the discount rate is 12%:

Project Year 0 Year 1 Year 2 Year 3 Year 4

X ($1,400) $350 $750 $650 $650

Y ($1,000) $300 $400 $500 $600

Calculate the Equivalent Annual Cashflow (EAC) for project X. (Please note that the answer is $127.13, but please provide steps and calculations on how to get this answer. Please show formulas if using excel)