Question: Consider the following work breakdown structure: ActivityStart NodeFinish NodeDuration ( days ) OptimisticMost LikelyPessimisticA 1 2 4 1 5 0 5 9 B 1 3

Consider the following work breakdown structure:
ActivityStart NodeFinish NodeDuration (days)OptimisticMost LikelyPessimisticA12415059B13546066C24587082D34324144
What is the probability that this project will be completed within 130 days?
Multiple Choice
.8413
.90
.9544
.9772
.9987