Question: Consider the following work breakdown structure: Time Estimates ( days ) table [ [ Activity , Precedes,Optimistic,Most Likely,Pessimistic ] , [ Start , A

Consider the following work breakdown structure:
Time Estimates (days)
\table[[Activity,Precedes,Optimistic,Most Likely,Pessimistic],[Start,A, B, C,-,-,-],[A,D,38,50,62],[B,E,90,99,108],[C,End,85,100,115],[D,F,19,25,31],[E,End,91,100,115],[F,End,62,65,68]]
What is the estimated slack time for activity A?
0 days
20 days
100 days
40 days
60 days