Question: Consider the following work breakdown structure: Time Estimates ( days ) Optimistic Most Likely Pessimistic Precedes Activity Start A , B C , D 4

Consider the following work breakdown structure: Time Estimates (days) Optimistic Most Likely Pessimistic Precedes Activity Start A , B C,D 4456 AB D 456075424548 F 314049 F 273639 End 587082 What is the estimated standard deviation in the time for activity E?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!