Question: Consider the following work breakdown structure: Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A,B,C - - - A D 38 50 62
| Consider the following work breakdown structure: | ||||||||||
| Time Estimates (days) | ||||||||||
| Activity | Precedes | Optimistic | Most Likely | Pessimistic | ||||||
| Start | A,B,C | - | - | - | ||||||
| A | D | 38 | 50 | 62 | ||||||
| B | E | 90 | 99 | 108 | ||||||
| C | End | 85 | 100 | 115 | ||||||
| D | F | 19 | 25 | 31 | ||||||
| E | End | 91 | 100 | 115 | ||||||
| F | End | 62 | 65 | 68 | ||||||
| what is the estimated slack time for activity A? | ||||||||||