Question: Consider the following work breakdown structure: Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A, B, C 38 90 85 19 91 62

 Consider the following work breakdown structure: Time Estimates (days) Activity PrecedesOptimistic Most Likely Pessimistic Start A, B, C 38 90 85 19

Consider the following work breakdown structure: Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A, B, C 38 90 85 19 91 62 50 62 108 115 31 115 68 End 100 25 100 65 End End What is the probability that this project will be completed within 205 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!