Question: Consider the following work breakdown structure Time Estimates (days) Most Likely Pessimistic Optimistic Precedes Activity A,B Start 56 50 44 C,D A 75 60 45

 Consider the following work breakdown structure Time Estimates (days) Most Likely

Consider the following work breakdown structure Time Estimates (days) Most Likely Pessimistic Optimistic Precedes Activity A,B Start 56 50 44 C,D A 75 60 45 B 48 45 42 F C 49 40 31 D 39 36 27 E 82 70 58 End E What is the estimated expected (mean) time for activity E? Multiple Cholce 35 days 36 days 39 days 40 days 45 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!