Question: 12 Consider the following work breakdown structure: Time Estimates (days)) Most Likely Activity Precedes Optimistic Pessimistic Start A,B nts ABCDEE C,D 44 50 56 D

 12 Consider the following work breakdown structure: Time Estimates (days)) Most

12 Consider the following work breakdown structure: Time Estimates (days)) Most Likely Activity Precedes Optimistic Pessimistic Start A,B nts ABCDEE C,D 44 50 56 D 45 60 75 E 42 45 48 F 31 40 49 F 27 36 39 F End 58 70 82 What is the probability that the critical path for this project will be completed within 210 days? Multiple Choice 8413 5000 9987 9772