Question: 12 Consider the following work breakdown structure: Time Estimates (days)) Most Likely Activity Precedes Optimistic Pessimistic Start A,B nts ABCDEE C,D 44 50 56 D

12 Consider the following work breakdown structure: Time Estimates (days)) Most Likely Activity Precedes Optimistic Pessimistic Start A,B nts ABCDEE C,D 44 50 56 D 45 60 75 E 42 45 48 F 31 40 49 F 27 36 39 F End 58 70 82 What is the probability that the critical path for this project will be completed within 210 days? Multiple Choice 8413 5000 9987 9772
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
