Question: Consider the following work breakdown structure: What is the estimated expected (mean) time (in weeks) for project completion? a.35 b.75 c.115 d.170
Consider the following work breakdown structure: What is the estimated expected (mean) time (in weeks) for project completion?
a.35
b.75
c.115
d.170