Question: Consider the information provided below for the project and answer the following questions. Activity Predecessor Duration (in days) A - 3 B A 4 C
Consider the information provided below for the project and answer the following questions.
| Activity | Predecessor | Duration (in days) |
| A | - | 3 |
| B | A | 4 |
| C | A | 5 |
| D | B, C | 2 |
| E | B, C | 3 |
| F | D, E | 4 |