Question: Consider the information provided below for the project and answer the following questions. Activity Predecessor Duration (in days) A - 3 B A 4 C

Consider the information provided below for the project and answer the following questions.

Activity

Predecessor

Duration (in days)

A

-

3

B

A

4

C

A

5

D

B, C

2

E

B, C

3

F

D, E

4

Question 7 options:

Determine the latest start time (LS) of activity B.

What is the slack time, in days, associated with activity E?

How long will take to complete the project?

Determine the latest finish time (LF) of activity B.

Determine the earliest start time (ES) of activity E.

1.

ACEF

2.

ABEF

3.

16 days

4.

15 days

5.

14 days

6.

2

7.

0

8.

1

9.

4

10.

5

11.

8

12.

10

13.

A

14.

C

15.

F

16.

E

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!