Question: Consider the network described in the table below. Immediate Predecessor(s) Pessimistic Probable 15 10 Activity J K L M N o P J J KM

Consider the network described in the table Consider the network described in the table

Consider the network described in the table below. Immediate Predecessor(s) Pessimistic Probable 15 10 Activity J K L M N o P J J KM KM LN 9 10 3 9 10 10 8 6 3 5 7 8 Optimistic 8 7 5 3 1 4 3 A) Draw the Network B) Complete the table below: Task Slack Variance Early Start Early Finish Late Start Late Finish Expected Tiine J K L M N O P C) What are the critical path activities? D) What is the project completion time? E) Calculate the project variance and standard deviation