Question: A Moving to another question will save this response. Question 18 Consider the network described in the table below. Immediate Predecessor(s) Pessimistic Activity Probable Optimistic

A Moving to another question will save this
A Moving to another question will save this
A Moving to another question will save this response. Question 18 Consider the network described in the table below. Immediate Predecessor(s) Pessimistic Activity Probable Optimistic J 15 10 8 K 9 8 7 L J 10 6 5 J 3 3 3 3 O Z3 KM 9 5 1 KM 10 7 4 P LN 10 8 3 What is the standdard deviation of this project? Moving to another question will save this response. Question 19 Consider the network described in the table below. Immediate Predecessor(s) Pessimistic Activity Probable Optimistic J 15 10 8 K 9 8 7 L 10 6 5 M J 3 3 3 N KM 9 5 1 o KM 10 7 P LN 10 8 3 What is the earliest Finish of activity O

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!