Question: Consider the network described in the table below. Time in weeks. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J -- 15 10 8 K -- 9

Consider the network described in the table below. Time in weeks.

Activity

Immediate

Predecessor(s)

Pessimistic

Probable

Optimistic

J

--

15

10

8

K

--

9

8

6

L

J

10

6

5

M

J

3

3

4

N

K,M

9

5

2

O

K,M

12

7

5

P

L,N

10

8

3

(a) Calculate the expected duration of each activity.

(b) Calculate the expected duration and variance of the critical path.

(c) Calculate the probability that the project will be completed in more than 26 weeks time? How about 30 weeks?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!