Question: Consider the network presented in the following table. Calculate the slack for activity D. (Enter your response to the nearest whole number.) Task Duration (Days)
Consider the network presented in the following table. Calculate the slack for activity D. (Enter your response to the nearest whole number.)
Task | Duration (Days) | Immediate Predecessors |
A | 50 | None |
B | 119 | A |
C | 40 | A |
D | 20 | C |
E | 10 | B, D |
Your Answer: