Question: Read the following instructions carefully. Make sure you carefully construct and fully label the diagrams. Neatness counts! Base your analysis on the information in the

Read the following instructions carefully. Make sure you carefully construct and fully label the diagrams. Neatness counts!
Base your analysis on the information in the table. A project has been defined to contain a list of activities/tasks (each identified by letter) along with the immediate predecessor activities and the optimistic, most likely, and pessimistic time estimates (in days) for completion.
1. Use the 3-point (PERT) method to calculate the normal duration for each task (round to the nearest whole number) and enter in table.
2. Construct a labeled network diagram (include duration, early/late times) on paper theninsert the image below the table (Or submit the image as another file)
3. Calculate and enter the free slack and total slack for each task in the table.
4. List all possible paths with durations and identify the critical path.
Activities Immediate Time Time Time Estimated Durations Free Slack Total Slack
Predecessors a m b
A - 8 10 18
B A 2 8 10 list all possible paths with duration and highlight the critical path:
C B 9 12 23 1
D A 15 16 22 2
E C, D 6 8 10 3
F D 4 9 10 4
G E, F 8 9 16

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!