Question: Consider the precedence with resources chart. Perform resource smoothing and pictorially represent resource smoothing. Activity Immediate Predecessors Duration in days Number of Painters Used A

Consider the precedence with resources chart. Perform resource smoothing and pictorially represent resource smoothing.

Activity Immediate Predecessors Duration in days Number of Painters Used
A - 5 3
B - 4 5
C A 7 3
D B 4 4
F - 3 3