Question: Consider the following precedence chart: Activity Immediate Predecessor Duration in days Number of Painters used A - 4 2 B - 6 4 C -

Consider the following precedence chart:

Activity Immediate Predecessor Duration in days Number of Painters used
A - 4 2
B - 6 4
C - 6 2
D A 4 2
E B 10 4
F C 2 1

Now apply the resource smoothing technique. For the first 14 days, the maximum number of painters needed is ____________andbetween the 14 th day and 16 th day, the maximum number of painters needed is _________.