Question: Consider the following precedence chart: Activity Immediate Predecessor Duration in days Number of Painters used A - 4 2 B - 6 4 C -
Consider the following precedence chart:
| Activity | Immediate Predecessor | Duration in days | Number of Painters used |
| A | - | 4 | 2 |
| B | - | 6 | 4 |
| C | - | 6 | 2 |
| D | A | 4 | 2 |
| E | B | 10 | 4 |
| F | C | 2 | 1 |
Now apply the resource smoothing technique. For the first 14 days, the maximum number of painters needed is ____________andbetween the 14 th day and 16 th day, the maximum number of painters needed is _________.