Question: Consider the programmers resource hlstogram presented in the flgure above. Which of the following describes the consequence you can expect by delaying activity C to

Consider the programmers resource hlstogram presented in the flgure above. Which of the following describes the consequence you can expect by delaying activity C to its late start date? a. You will make this project schedule resource feasible. b. You will delay the project completion by 6 weeks. c. You will simply delay the resource overload. d. None of the above