Question: Consider the programmers resource hlstogram presented in the flgure above. Which of the following describes the consequence you can expect by delaying activity C to

 Consider the programmers resource hlstogram presented in the flgure above. Which

Consider the programmers resource hlstogram presented in the flgure above. Which of the following describes the consequence you can expect by delaying activity C to its late start date? a. You will make this project schedule resource feasible. b. You will delay the project completion by 6 weeks. c. You will simply delay the resource overload. d. None of the above