Question: Consider the project described by the table below where all durations are in days and, the normal and crash costs are in Ghana Cedis. In
Consider the project described by the table below where all durations are in days and, the normal and crash costs are in Ghana Cedis. In addition, there is a fixed cost of GHS1000 for each day on site.
| Activity | Predecessor | Normal Time | Normal Cost (GHS) | Crash Time | Crash Cost (GHS) |
| A |
| 2 | 2,000 | 2 | 2,000 |
| B |
| 13 | 2,000 | 10 | 2,300 |
| C |
| 19 | 2,000 | 15 | 3,000 |
| D | A | 18 | 2,000 | 15 | 3,000 |
| E | B | 13 | 2,000 | 11 | 3,000 |
| F | C | 10 | 2,000 | 9 | 3,000 |
| G | D | 18 | 2,000 | 14 | 4,000 |
| H | E | 6 | 2,000 | 5 | 3,000 |
| I | F | 4 | 2,000 | 3 | 3,000 |
| J | G | 13 | 2,000 | 12 | 3,000 |
| K | H,I | 15 | 2,000 | 13 | 3,000 |
| L | J,K | 4 | 2,000 | 4 | 2,000 |
Given this information, the total cost of the project (before any crashing is performed) is GHS _____________________________________ .