Question: Consider the project described by the table below where all durations are in days and, the normal and crash costs are in Ghana Cedis. In

Consider the project described by the table below where all durations are in days and, the normal and crash costs are in Ghana Cedis. In addition, there is a fixed cost of GHC1000 for each day on site.

Activity Predecessor Normal Time Normal Cost (GHC) Crash Time Crash Cost (GHC)

A 2 2,000 2 2,000

B 13 2,000 10 2,300

C 19 2,000 15 3,000

D A 18 2,000 15 3,000

E B 13 2,000 11 3,000

F C 10 2,000 9 3,000

G D 18 2,000 14 4,000

H E 6 2,000 5 3,000

I F 4 2,000 3 3,000

J G 13 2,000 12 3,000

K H,I 15 2,000 13 3,000

L J,K 4 2,000 4 2,000

If the project is to be completed in 53 days, the minimum total cost of the project will be GHS?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!