Question: Consider the project given in the table below. The activities, predecessors, normal durations, normal cost, crashability, cost slope, the resources usage and resource limits are

Consider the project given in the table below. The activities, predecessors, normal durations, normal cost, crashability, cost slope, the resources usage and resource limits are shown in the table.
\table[[Activity,Predecessors,Normal,Crashability (Weeks),\table[[Cost slop],[(SR/week)]],Resource Rate],[\table[[Duration],[(Weeks)]],Cost (SR),Resource I 9 units,Resource II 9 units],[A,---,2,2400,-,-,3,1],[B,A,8,9600,2,200,4,6],[C,A,6,4800,2,50,7,6],[D,A,4,1200,1,200,6,5],[E,A,3,2700,-,-,4,1],[F,B,12,7200,4,100,2,0],[G,C, D,4,4000,1,75,7,9],[H,D, E,6,6000,3,100,6,4],[K,F, G, H,3,2100,-,-,2,0]]
c. Consider the same project presented in the table and assume that the indirect cost of this project is LE100/week.
i. Find the optimum project duration and the total project cost at that duration.
(4 marks)
ii. What is the minimum project duration and the total cost at that duration?
(4 marks)
 Consider the project given in the table below. The activities, predecessors,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!