Question: Exercise 5 Consider the project given in the table below. The activities, predecessors, normal durations, normal cost, crashability, cost slope, the resources usage and resource

Exercise 5
Consider the project given in the table below. The activities, predecessors, normal durations, normal cost, crashability, cost slope, the resources usage and resource limits are shown in the table.
\table[[Activity,Predecessors,Normal,Crashability (Weeks),\table[[Cost slop],[(SR/week)]],Resource Rate],[\table[[Duration],[(Weeks)]],Cost (SR),Resource I 9 units,Resource II 9 units],[A,---,2,2400,-,-,3,1],[B,A,8,9600,2,200,4,6],[C,A,6,4800,2,50,7,6],[D,A,4,1200,1,200,6,5],[E,A,3,2700,-,-,4,1],[F,B,12,7200,4,100,2,0],[G,C, D,4,4000,1,75,7,9],[H,D, E,6,6000,3,100,6,4],[K,F, G, H,3,2100,-,-,2,0]]
a. Determine the project completion date and mark the critical path. Calculate the activities free and total floats.
(5 marks)
b. Assume that only 9 units are available from each resource. Calculate the activities start and finish dates that satisfies the resources constraints "Resource Scheduling".
(7 marks)
c. Consider the same project presented in the table and assume that the indirect cost of this project is LE100/week.
i. Find the optimum project duration and the total project cost at that duration.
(4 marks)
ii. What is the minimum project duration and the total cost at that duration?
(4 marks)
 Exercise 5 Consider the project given in the table below. The

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!