Question: Consider the project information in Table 1 , showing the WBS elements comprising the entire scope of a project, planned dates in baseline schedule, and

Consider the project information in Table 1,
showing the WBS elements comprising the entire
scope of a project, planned dates in baseline
schedule, and actual/planned in updated schedules.
The projects planned duration was 100 days.
Measurement of work element progress is by the
duration method.
i. Draw the baseline schedule of the project as a
bar chart.
ii. Draw the updated schedule for 3rd update as a
bar chart; Data Date (DD)=75d
(Hint: you can combine bar charts for baseline
and updated schedules in one chart, if you
prefer)
iii. Calculate the planned project progress by time from the baseline schedule.
iv. Calculate the actual project progress on the DD of 75d.
v. Comment on the project time performance using:
a. Project progress
b. Project updated completion date
vi. Analyze the reasons of delay
vii. Suggest suitable managerial actions to mitigate (overcome) the delays
WBS
Element
Baseline
Schedule
Schedule
Update 3
(DD =75d)
Start (d) Finish
(d)
Start
(d)
Finish
(d)
A 0100- A 11- A
B 102010- A 23- A
C 107011- A 77
D 104012- A 51- A
E 7010077115
*"A" denotes an actual date, e.g."11- A" means an

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!