Question: Consider the project information in the table: Activities Duration ( days ) Immediate Predecessor ( s ) A 6 - - - - B 2

Consider the project information in the table:
Activities Duration (days) Immediate Predecessor(s)
A 6----
B 2----
C 3 A
D 5 A
E 3 A
F 2 C
G 3 E
H 4 B,E
I 2 H
J 2 F,G,I
a. What is the slack in task F ?(4 points)
b. Suppose the project has just been started. What is the longest you could delay beginning work on activity A without delaying the completion of the project? (3 points)
c. What is the earliest that activity G can be completed? (4 points)
d. What is the most likely that activity D can be delayed without delaying the project? (4 points)