Question: Consider the project information in the table: Activities Duration ( days ) Immediate Predecessor ( s ) A 6 - - - - B 2
Consider the project information in the table:
Activities Duration days Immediate Predecessors
A
B
C A
D A
E A
F C
G E
H BE
I H
J FGI
a What is the slack in task F points
b Suppose the project has just been started. What is the longest you could delay beginning work on activity A without delaying the completion of the project? points
c What is the earliest that activity G can be completed? points
d What is the most likely that activity D can be delayed without delaying the project? points