Question: Consider the project information in the table below (time in days): Immediate Predecessor a m 30 40 35 30 40 50 Activity A B D

Consider the project information in the table

Consider the project information in the table below (time in days): Immediate Predecessor a m 30 40 35 30 40 50 Activity A B D E F G H 1 J A A B D D G E/F HI 20 60 75 45 50 20 40 30 100 85 60 60 25 50 b 50 70 60 40 140 125 75 130 60 60 1 1 Construct the PERT network diagram. 2 Compute for the mean (t) and variances for each activity. 3 What is the Critical Path? 4 What is the expected length of the critical path? 5 What is the probability of meeting the 300-day deadline