Question: Consider the project performance report presented in Figure 1 4 - 1 . As a project manager these results should lead you to: Question 2
Consider the project performance report presented in Figure As a project manager these results should lead you to:
Question Answer
a
notify the project owner that you will not require all of the funding currently budgeted for this project.
b
take actions to understand and remedy the schedule performance on the active avionics work packages.
c
take actions to understand and resolve budgetary overruns on the active communications work packages.
d
take actions to understand and remedy the schedule performance on the active training work packages.