Question: Consider the project performance report presented in figure 1 4 . 1 . As a project manager, these results should lead you to . .

Consider the project performance report presented in figure 14.1. As a project manager, these results should lead you to...
WBS Element
Planned Value
(PV)
Earned Value
(EV)
Actual Cost
(AC)
2.01 Airframe
48000
48000
50000
2.02 Engines
22000
21000
23000
2.03 Avionics
80000
60000
45000
2.04 Communications
30000
30000
30000
2.05 Tech. Manuals
42000
42000
48000
2.06 Spares
40000
35000
42000
2.07 Training
80000
80000
86000
Project Total
342000
316000
324000
Figure 14.1 Drug Surveillance Aircraft Project - Monthly Performance Report
(October 31,20XX)
Question 21 options:
1)
take actions to understand and remedy the schedule performance on the active avionics work packages.
2)
take actions to understand and resolve budgetary overruns on the active communications work packages.
3)
take actions to understand and remedy the schedule performance on the active training work packages.
4)
notify the project owner that you will not require all of the funding currently budgeted for this project.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!