Question: Consider the project schedule shown in the table below. Times are given in days. Activity Predecessor(s) Duration ES EF LS LF Slack A - 2
Consider the project schedule shown in the table below. Times are given in days.
| Activity | Predecessor(s) | Duration | ES | EF | LS | LF | Slack |
| A | - | 2 | 0 | 2 | 0 | 2 | 0 |
| B | A | 7 | 7 | ||||
| C | A | 4 | 2 | 6 | |||
| D | B | 2 | 7 | 9 | 17 | 10 | |
| E | B, C | 4 | 7 | 11 | 7 | 11 | 0 |
| F | C | 5 | 6 | 11 | 0 | ||
| G | E, F | 8 | 11 | 19 | 11 | 0 |
What is the LS time for activity B?
The LS time for activity B is enter your response here days.
What is the project duration?
The project duration is enter your response here days.
What are the critical activities?
(Enter your answer as a sequence of capital letters with no dashes or spaces.)
The critical activities are enter your response here.
Step by Step Solution
3.52 Rating (159 Votes )
There are 3 Steps involved in it
To find the LS time for activity B we need to use the information provided in th... View full answer
Get step-by-step solutions from verified subject matter experts