Consider the project schedule shown in the table below. Times are given in days. Activity Predecessor(s) Duration
Fantastic news! We've Found the answer you've been seeking!
Question:
Consider the project schedule shown in the table below. Times are given in days.
Activity | Predecessor(s) | Duration | ES | EF | LS | LF | Slack |
A | - | 2 | 0 | 2 | 0 | 2 | 0 |
B | A | 7 | 7 | ||||
C | A | 4 | 2 | 6 | |||
D | B | 2 | 7 | 9 | 17 | 10 | |
E | B, C | 4 | 7 | 11 | 7 | 11 | 0 |
F | C | 5 | 6 | 11 | 0 | ||
G | E, F | 8 | 11 | 19 | 11 | 0 |
What is the LS time for activity B?
The LS time for activity B is enter your response here days.
What is the project duration?
The project duration is enter your response here days.
What are the critical activities?
(Enter your answer as a sequence of capital letters with no dashes or spaces.)
The critical activities are enter your response here.