Question: Consider the project shown below. Max Crash time indicates the most days that a task can be crashed (Normal time crash time). a.Draw the network
Consider the project shown below. Max Crash time indicates the most days that a task can be crashed (Normal time crash time).
a.Draw the network diagram by hand and find the critical path, time and cost for an all-normal level of project activity.
b.Calculate the crash cost-per-day assuming that all activities may be partially crashed (except C and H which cannot be crashed).
c.Which tasks should be crashed to do the project in 27days? Calculatethe cheapest project costat that duration.