Consider the set of 7 processes whose arrival time, burst time, and priority are given below: Process P1 P2 P3 P4 P5 PO P7 Arrival Time 0 1 3 4 5 6 10 Burst Time 8 2 4 1 6 5 1 Priority 3 4 4 5 2 6 1 Using the nonpreemptive priority scheduling algorithm, calculate the average turnaround time and the average waiting time. The average turnaround time is The average waiting time is