Question: Consider the System Integration Project depicted in Figure 8 - 3 . Based on the information provided, how many days can you delay the purchase

Consider the System Integration Project depicted in Figure 8-3. Based on the information provided, how many days can you delay the purchase of software (Activity C), without impacting the expected project completion date?m(it is NOT 0 days)
Figure 8-4 Lab Experiment Project
0 days
1 day
2 days
4 days
 Consider the System Integration Project depicted in Figure 8-3. Based on