Question: Consider the table below. All duration estimates are in days, and the network proceeds from node 1 to node 8. - Use the MS Word
Consider the table below. All duration estimates are in days, and the network proceeds from node 1 to node 8.
- Use the MS Word drawing tool to draw an AOA network diagram representing the project.
- What is the critical path for this project and how long is it? Provide detailed explanation.
| Activity | Initial Node | Final Node | Estimated duration |
| A | 1 | 2 | 2 |
| B | 2 | 3 | 2 |
| C | 2 | 4 | 3 |
| D | 2 | 5 | 6 |
| E | 3 | 6 | 2 |
| F | 4 | 6 | 3 |
| G | 5 | 7 | 5 |
| H | 6 | 8 | 2 |
| I | 6 | 7 | 5 |
| J | 7 | 8 | 1 |