Question: Consider the two projects depicted in Table 2: The net present value (NPV) of project B is ________. Note: Express your answers in strictly numerical
"Consider the two projects depicted in Table 2: The net present value (NPV) of project B is ________. Note: Express your answers in strictly numerical terms. For example, if the answer is $500, write enter 500 as an answer."
"Consider the cash flow of the two projects depicted in Table 3. If WiseGuy Inc. uses payback period rule to choose projects, which of the projects (Project A or Project B) will rank highest? --- Project A. Project B. Project A and Project B have the same ranking. Cannot calculate a payback period without a discount rate. "
| Table 3 | ||
| Project A | Project B | |
| Time 0 | -12,000 | -3,000 |
| Time 1 | 7,000 | 3,000 |
| Time 2 | 9,000 | 3,000 |
| Time 3 | 12,000 | 1,000 |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock