Question: Consider the weekly data in the following table: 1 3 5 Period Gross requirements 2 20 4 40 We have 30 units on hand as

Consider the weekly data in the following table:

Consider the weekly data in the following table: 1 3 5 Period Gross requirements 2 20 4 40 We have 30 units on hand as inventory. Lead time is one week. We are going to use lot-for-lot ordering strategy to develop an MRP (i.e., order sizes are equal to net requirements). What is the projected on hand in Week 3? 10 20 30 0 40 What is the planned order release in Week 3? 20 0 30 10 40