Question: Consider this information: Path 1: A-B-E-H-K = 10 days Path 2: A-C-F-H-K = 12 days Path 3: A-C-F-I-J-K= 16 days Path 4: A-D-G-J-K = 15

Consider this information:

Path 1: A-B-E-H-K = 10 days

Path 2: A-C-F-H-K = 12 days

Path 3: A-C-F-I-J-K= 16 days

Path 4: A-D-G-J-K = 15 days

knowing that the critical path is path 3 .

Question: What is the earliest time all tasks can be completed?( the answer is not path 1 , because it will not complete all tasks.)