Question: Consider this information: Path 1: A-B-E-H-K = 10 days Path 2: A-C-F-H-K = 12 days Path 3: A-C-F-I-J-K= 16 days Path 4: A-D-G-J-K = 15
Consider this information:
Path 1: A-B-E-H-K = 10 days
Path 2: A-C-F-H-K = 12 days
Path 3: A-C-F-I-J-K= 16 days
Path 4: A-D-G-J-K = 15 days
knowing that the critical path is path 3 .
Question: What is the earliest time all tasks can be completed?( the answer is not path 1 , because it will not complete all tasks.)